[nws-changes] 20070827: NP changes

NOTE: The nws-changes mailing list is no longer active. The list archives are made available for historical reasons.

Subject:
GINI Transition -- Final Steps:ISSUED 08/27/07 17:-00 UTC
From:
ESPCoperations <ESPCoperations@xxxxxxxx>
Date:
Mon, 27 Aug 2007 13:02:53 -0400
To:
_NESDIS OSDPD ESPC OUTAGE Notification <ESPC.Notification@xxxxxxxx>

Around 13:05 PM we will be transitioning from Nport1 to Nport3.

August 27 - switch from NPORT1 to NPORT3 for primary operations; test NPORT3 transmissions including the four satellite composite available from gp12 - following above test or performed concurrently, test NPORT4 transmissions to BNCF

August 28 - if above tests are successful, have Dale H. come to the WWB to remove remaining network cables from GINI and install on NSOF GINI; at this time, the WWB GINI is decommissioned; after cable installation at NSOF GINI, declare system for primary and back-up operational production and dissemination

Contact Point for Questions:
ESPC Operations  OCL (Operations Crew Leader),  301-817-3880