[nws-changes] [20090508: Upcoming GOES-O Events]

NOTE: The nws-changes mailing list is no longer active. The list archives are made available for historical reasons.


-------- Original Message -------


GOES-O Significant Events:

Remaining Liquid Apogee Motor (LAM) burns:
3 - July 4, 2009
4 - July 6, 2009
5 - July 8, 2009
Solar Array Deployment - July 9, 2009
Magnetometer Boom Deployment - July 13, 2009
Post Launch Testing (PLT) starts - July 17, 2009
Engineering Handover to NASA - July 18, 2009
SXI Software 6.29 Memory Load – July 21, 2009
XRP Deployment – July 24, 2009
XRS/EUV Power-on – July 24, 2009
First Public Imager Full Disk Images - July 28, 2009
First Public SXI Image – August 6, 2009
Drift Control maneuver – August 7, 2009
Imager & Sounder Cooler Cover Deployments – August 15, 2009
First Public IR Images – August 17, 2009
INR Start-up - 8/27/09 to 9/4/09
Contingency Operations Readiness Review (CORR) - 9/11/09
Image Motion Compensation Spec Testing - 9/14/09 to 10/30/09
NSSK 1 Maneuver - 10/31/09
EWSC to 105W Maneuver - 11/10/09 to 11/22/09
NSSK 2 Maneuver - 11/28/09
NOAA Science Testing - 12/01/09 to 12/15/09
Operations Acceptance Review (OAR) - 12/15/09
Post Launch Testing Ends and handover to NOAA- 12/15/09